First power
Grid-supplied first, then on-site generation to the anchor tenant from July 2027.

A powered shell behind the meter. Delivery follows Fermi’s construction schedule, not an interconnection queue.
Capacity is released as construction phases complete.
Grid-supplied first, then on-site generation to the anchor tenant from July 2027.
The nine turbines already in Texas, installed and generating.
If the Hillcore alliance reaches definitive agreements and is built.
Subject to permits, land closings and financing. Nuclear in the 2030s if licensed.

The TensorWave lease is the template: phased delivery against construction, a 15-year initial term running from the final phase, two five-year renewals, and expansion options. A tenant may also bring its own power configuration instead of taking Fermi generation.

Tell us the capacity and timing you need. Fermi scopes technical fit and delivery phases with each prospective tenant.
