Concept render
← Fermi
For hyperscalers

Capacity, on schedule.

Buying GPUs takes a quarter; powering them takes years. Fermi delivers the scarce half, energized, behind-the-meter gigawatts on a construction schedule, not a utility waiting list.

1.5GW
Staged by end of 2027
700KGPUs/GW
Data center density
345kV
Private campus bus
15M+ FT²
Data center capacity
The clock

Your schedule is now gated by megawatts, not GPUs.

The chips ship in a year. The power is the long pole. Here is the honest distance to an energized gigawatt, and why Fermi is measured in quarters, not presidential terms.

Utility interconnectionPlug new load into the public grid
36–84 mo
Greenfield self-buildPermit and build a new site from zero
48–60 mo
Fermi HyperGridPermitted · turbines staged · in construction
12–24 mo

First power Q1 2027. While a fresh queue request is still drawing up paperwork, your first blocks are already energizing, up to five years sooner.

The site

Project Matador, engineered.

7,570 acres in Carson County, Texas, a 4,617-acre main campus beside the DOE's Pantex plant, with workforce housing, incoming water and gas across FM 683, two data-center parcels, an on-site response center, and a Fiberlight dark-fiber node at the rail corridor.

U.S. DOE · PANTEX PLANT (ADJACENT)RESTRICTED FEDERAL LANDRAIL + LONG-HAUL FIBER CORRIDORPROJECT MATADOR · 7,570 ACTEXAS TECH UNIVERSITY SYSTEM LANDS · CARSON COUNTY, TXPLAYAFM 683WORKFORCE HOUSING+/- 300 ACRESMAIN CAMPUS · 4,617 ACRESINCOMING WATER · 2.5–5.5 MGDINCOMING GAS · MAJOR PIPELINESCCGT G1–G6 · 6.0 GW PERMITTEDG1·27G2·27G3·27G4·28G5·29G6·29NUCLEAR · 4 × AP1000 · FILED WITH NRCCOD 2031–32SOLAR · 2.0 GW PEAKBESS · 1.5 GW / 6 GWHPRIVATE SWITCHYARD · 345 KVBEHIND-THE-METERDATA CENTER · 380 ACRESD1 · 3-STORY · LIQUID-COOLEDPHASED 2027 →FIRE & EMERGENCYRESPONSE CENTERDATA CENTER · 397 ACRESD5 · 2-STORYFIBERLIGHT NODE24 STRANDS AVAILABLE · DARK FIBERNFERMI · PROJECT MATADOR · SITE PLANAFTER THE MASTER PLAN · NOT FOR CONSTRUCTIONSHT A-101 · GENERATED IN CODE · REV 2026.06
Explore the campus
Hover or tap a marker on the plan, each system, sized and sited.
Reservation model

Reserve capacity in waves.

WAVE 1 · 2027
1.5 GW

First power

Initial gas blocks energize. Anchor positions for pilot clusters and time-critical training capacity. The scarce wave, finite by physics, not marketing.

WAVE 2 · 2028
2.3 GW

Acceleration

Equipment facility pulling turbine deliveries forward. Battery storage online for step-load smoothing and checkpoint-safe ride-through.

WAVE 3 · 2029
6.0 GW

Full gas fleet

The complete permitted CCGT complex plus utility-scale solar. Campus operating at the scale of a major city; majority of shells delivered.

WAVE 4 · 2031+
→ 17 GW

The nuclear era

As AP1000s energize, contracted blocks are designed to migrate onto low-carbon baseload, with CFE reporting targeted to become hourly-matched without leaving the fence.

Your contracted capacity requirement.
When your clusters must energize.
Assumptions: 5.5-year queue for a request filed today; $90/MWh contracted power; 700k accelerators per GW. Illustrative, from public reporting.

A 1.5 GW block needed by 2027 fits Wave 1, energizing 2027. A fresh interconnection request filed today reaches commercial operation around 2032, Fermi hands you 54 months of compute head start.

Wave 1 · 2027
Your wave · energized
54 months
Head start vs the queue
$5.3B
Head-start value · contracted power
1.1M
Accelerators deployed early
The reckoner is illustrative arithmetic, not an offer of capacity.
The advantage

Behind the meter, by design.

Generation, switchyard, fiber, and shell are designed as one program on one private 345 kV bus, behind the meter and independent of the public grid for the load. Designed to avoid the interconnection queue and to reduce transmission and curtailment risk. Capacity is planned to arrive on a construction schedule, not a regulator's calendar.

Behind the meter, by design.
Inside the fence

Specifications, against your SLA.

  • Site7,570 contiguous acres in Carson County, TX, adjacent to DOE Pantex. Phased expansion without re-permitting land.
  • Generation6 GW CCGT + 4×AP1000 (4.4 GW) + 2 GW solar/BESS + 1 GW grid tie, four independent failure domains, real N+1 across fuel, weather, and mechanical risk.
  • Shells15M+ ft² across 15 data centers, liquid-cooling-first. Power-shell co-design for 100 kW+ racks, no retrofit tax.
  • FuelFive major pipelines within 20 miles, 340+ MMBtu/d secured; the site sits at the intersection of two.
  • FiberRedundant long-haul at site, Dallas 7.1 ms, OKC 5.0 ms, Denver 8.3 ms round-trip.
  • Water11 MGD from multiple sources, 2.5 MGD already on site; nuclear under 50 acre-ft/yr.
  • Carbon pathGas-led in 2027, targeting a majority low-carbon mix by the mid-2030s as nuclear energizes. On-site, hourly-matched CFE is a design goal, not REC arbitrage, for 24/7 pledges.
How it works

Reserve, then build against milestones.

Contract gigawatts in waves tied to construction. Bring your own power profile or take the integrated build. Talk to our team to scope capacity, timing, and technical fit.

Reserve, then build against milestones.
The decision

Three ways to get a gigawatt. One that clears every row.

How it's judged
Grid + firm PPA
Greenfield self-build
Fermi HyperGrid
Time to first power
3–7 years
4–5 years
12–24 months
Interconnection queue
Required
Required
None · behind the meter
Transmission & curtailment risk
Inherited
Inherited
Designed out
Training load-step stability
Grid's worst day
You engineer it
Inertia + BESS on one bus
24/7 low-carbon path
RECs / arbitrage
Do it yourself
On-site nuclear + solar
High-density readiness
Retrofit tax
You design it
Power-shell co-design · 100 kW+
Control of your SLA
Contractual only
Full, but slow
Assets you can walk to

Same physics, three contracts. Only one puts the generation inside your fence.

Questions

Good to know.

Reserve your gigawatt.

Tell us your capacity and timeline. We confirm reservations in waves against construction.

We reply within two business days. This form is an expression of interest only and does not create a contract, reservation, or commitment by either party; capacity is allocated in waves against the construction schedule.

Private power. Hyperscale ready. Project Matador, a planned large-scale energy and AI campus in Amarillo, Texas.

620 S. Taylor, Suite 301
Amarillo, Texas 79101

© Fermi America. All rights reserved. This is an independent design study, not the official Fermi America website. Nothing here is an offer to sell or a solicitation of an offer to buy any security, and it is not investment advice; the contact form is an expression of interest only and creates no contract or reservation. This site contains forward-looking statements that involve risks and uncertainties; capacity, schedule, job, financial and environmental figures are targets, plans, or design estimates, not measured results or guarantees, and actual results may differ materially. Environmental and water comparisons refer to design specifications versus conventional alternatives and depend on facilities not yet built or licensed. Permits and licenses are at the status shown (e.g., applications filed or under review) and are not assured. For current, authoritative figures and disclosures, refer to Fermi America's official SEC filings.