Project Matador · 7,570 acres

This is what 17 gigawatts looks like.

One of the largest planned energy-and-AI campuses of its kind, rising on the Texas Panhandle beside the Department of Energy’s Pantex plant. Four data-center campuses, 11 GW of gas, 6 GW of nuclear (four AP1000 reactors plus SMRs), plus solar and storage, all behind one private fence.

See the master plan ↓
Campus Technology

The campus is the power plant.

Most data centers rent power from a grid that can’t grow fast enough. Fermi builds the generation and the load together, on the same 7,570 acres, behind one private 345 kV bus, so the place and the machines are a single system. Below: the master plan, the machines, and the ramp that bring it online.

  • 17 GWGas · nuclear · solar · storage
  • 15M ft²AI data centers, fed behind the meter
  • Q1 2027First power, targeted
The master plan

Every gigawatt, every acre, every corridor.

The full Project Matador layout, four data-center campuses, 11 GW of gas, 6 GW of nuclear, solar, and the private infrastructure corridors that feed them. Flip between the schematic and the real satellite plan, tap any parcel for detail, and toggle the infrastructure layers.

Understand the campus
PROJECT MATADOR · AMARILLO, TXHWY 60FM 683FM 2373DEPARTMENT OFENERGY · PANTEXMain Campus4,617 ACRES · DATA CENTERSLake Solar+100 acresWest Campus798 acresdata centersNuclear4.4 GW4× AP1000Substation345 kV busGas · 5.6 GWTurbine fleetSouth Campus1,236 acresdata centersEast Campus713 acresdata centersGas · 4.4 GWEast fleetWorkforce HousingWater TreatmentN1 MILE
7,570
total acres
11 GW
gas turbines
6 GW
nuclear (AP1000 + SMR)
15M ft²
data centers
Engaged with established institutions
  • Westinghouse AP1000 licensing
  • NRC · COL application filed
  • Adjacent to DOE Pantex
  • Texas Tech University System ground lease
Now look closer · the machines

Four sources. One bus. Fifteen data centers.

Every class of equipment in the plan is proven: combined-cycle gas turbines, AP1000 reactors, utility-scale solar, and grid batteries are all in commercial service today at sites around the world. Power is designed to flow from the generation fleet through a private 345 kV bus into the data centers, behind the meter; a modest ~200 MW tie to Xcel provides backup and start-up support, but the public grid is not built to carry the campus load.

The HyperGrid · behind the meter
17.0 GW
Planned generation
6 GW
Texas (TCEQ) air permit issued
NATURAL GAS11 GW PLANNED · 6 GW PERMITTEDNUCLEAR · AP1000 + SMR6 GW PLANNED (4.4 AP1000 · 1.6 SMR)SOLARCOMPLEMENTARY · DAYTIMESTORAGE · BESSCOMPLEMENTARY · BATTERYPRIVATE CAMPUS BUS345 KV · BEHIND THE METER · NO QUEUESTEP-DOWN15 AI DATA CENTERS700,000 GPUS / GWINTELLIGENCETOKENS · MODELS
6 GW issued
Texas (TCEQ) air permit
1.5 GW staged
By end of 2027
Q1 2027
First power, targeted
1st in 15 yrs
NRC combined license accepted
The fleet

Each machine has a job.

Combined-cycle gas

Combined-cycle gas

Two generations of power from one unit of fuel, today's firm megawatts, fed by pipelines at the fence.

AP1000 nuclear

AP1000 nuclear

Designed for passive safety and low-carbon baseload for decades, with roughly 72 hours of passive cooling per the AP1000 design. Four units filed with the NRC (license under review).

Solar

Solar

The Panhandle's cheapest energy, every daylight hour on the campus.

Storage

Storage

Batteries answer in milliseconds, riding through every training-load step.

The gas fleet

Three proven turbines.

Up to 11 GW of natural gas isn't one machine. It's three battle-tested models, staged in waves so megawatts land on a construction schedule.

Siemens SGT-800 gas turbine
6 units · 50–62 MW each

Siemens SGT-800

Millions of fleet hours worldwide. The first six landed at the Port of Houston; six more are financed for 2028, roughly the first gigawatt.

F-class · SGT6-5000F gas turbine
3 units · ~1.1 GW combined-cycle

F-class · SGT6-5000F

Heavy-duty F-class machines run in combined cycle, two generations of power from one unit of fuel, for the firm baseload tier.

GE Frame 6B gas turbine
3 units · 114 MW simple · 200+ MW CC

GE Frame 6B

Refurbished workhorses, fast to stage and proven for decades, early megawatts on the ground while the larger fleet arrives.

Concept renders · models per Fermi disclosures

The ramp

Capacity, on a schedule.

Nothing here waits on an interconnection queue. The turbines are bought, financed, and staged.

Q1 2027
200 MW · first power
1.5GW
End of 2027
2GW
2028
17GW
Up to, at full build

Private power. Hyperscale ready. Project Matador, a planned large-scale energy and AI campus in Amarillo, Texas.

620 S. Taylor, Suite 301
Amarillo, Texas 79101

© Fermi America. All rights reserved. This is an independent design study, not the official Fermi America website. Nothing here is an offer to sell or a solicitation of an offer to buy any security, and it is not investment advice; the contact form is an expression of interest only and creates no contract or reservation. This site contains forward-looking statements that involve risks and uncertainties; capacity, schedule, job, financial and environmental figures are targets, plans, or design estimates, not measured results or guarantees, and actual results may differ materially. Environmental and water comparisons refer to design specifications versus conventional alternatives and depend on facilities not yet built or licensed. Permits and licenses are at the status shown (e.g., applications filed or under review) and are not assured. For current, authoritative figures and disclosures, refer to Fermi America's official SEC filings.